Minth automotive Europe

Minth automotive Europe

For this project, the thermotechnical installation of heating, air conditioning and ventilation in the administrative parts of the plant Plant 1 and Plant 4.

In the production part of the Plant 1 facility, mechanical installations for pipe distribution of natural gas, compressed air, cooling water and technical water were carried out.

In addition, the pipe installation of the above-ground hot water pipe was carried out.

Pipe installation of the above-ground hot water pipe includes installation from the entrance to the hall all the way to the substation, assembly of the complete substation for heating and cooling the administrative part.

Also a chiller plant on the roof of the building, manufactured by Carrier.

minth-11
minth-22

Client

Minth automotive Europe

Date

November 2019 – February 2020

Place

Loznica